The House Of Redemption's Timeline
Planning the End from the Beginning | 2012-2015
Fall 2012
● Founder and Executive Director, Rev. Cynthia F. Burse, began work on her Doctor of Ministry degree, concentration, “Prisons,
Public Policy and Transformative Justice”
2013–2015
● 2013-2015: Fundraising and planning conversations regarding the construction of a container home. In May, Rev. Dr. Cynthia F.
Burse completed her degree
Securing the Property | 2016-2017
2016
● June: Initial meeting with Columbus Landbank regarding purchase of parcel number 010-033647
● July: Signed Architect Concept Design Proposal
● December: Received preliminary construction costs with Contractor (Hamilton Construction)
2017
● January-April: Proof of funding submitted and building contracts drafted
● May: Met with Area Commission Members
● June: Received letter from Columbus Landbank approving parcel purchase. Property survey completed
● July: During open hearing, received formal approval from Columbus City Council for construction project
● August: Closed on parcel 010-033647
● September-December: Building contract signed
Building the Foundation | 2018-2020
2018
● January: Construction drawings submitted to Columbus Building Department. THOR featured in Columbus Dispatch news article
● February: Conditional building permit received
● May: Received tap cards for water and sewer
● June-December: Containers delivered. Site excavation and footing work began
2019
● March: Inspection of footers approved
● September: Contractor delays
2020
● February: The emergence of the COVID-19 pandemic, which caused widespread supply chain disruptions and operational
shutdowns
● July-November: Gravel and concrete delivery and application
● December: Containers placed on the foundation
Setbacks and Challenges | 2021-2023
2021
● May-July: Containers fabricated
● August: Attempts to resolve Contractor problems
● September: Formal contractor complaint submitted to Columbus Building Department. Architect Drawing Revisions/Building
Permit changes
2022
● January: Contract signed with new contractor
● August: New containers delivered in Cleveland, OH for fabrication
2023
● May-June: New containers delivered to Columbus site. Roof, windows, and siding installed
● October: Executive Director of THOR, Rev. Cynthia Burse, became the official Contractor**
● November-December: Violations addressed and corrected. Steel report obtained and truss deficits corrected. Insulation installed
by Koala Insulation and thermostat installed by Sub Zero Heating & Air Conditioning. Plumbing issues addressed. Skirt boards
installed and backfill completed. Debris removed from the yard
Residential Occupancy and Pressing Onward | 2024-Present
2024
● January: Drywall installed by Olympic Drywall
● February-April: Kitchen equipment and cabinets installed. Bathroom shower, toilet, and sink installation completed. Interior
doors installed. Door and base molding installed. Caulking completed. Stone walkway installed in front and back
● April-May: Final inspections completed
● June: Occupancy permit received
● July-September: Resident applications reviewed
● October: First resident moves in!
2025
● June-Successful Financial Review of THOR
2026
● July: Began work to establish a broad community alliance
*In 2023, The House of Redemption received a settlement from Hamilton Rebuilder/Remodeler, Columbus, Ohio
+In April 2026, judgment was granted to The House of Redemption by the Columbus, OH Court of Common Pleas against Contractor Defendant Container Homes, USA, LLC, Cleveland, OH